By CBS Baltimore Staff

BALTIMORE (WJZ) — A crane arrived Saturday morning to remove the scaffolding that hung from the side of the BGE building in downtown Baltimore days after an explosion inside the building sent nearly two dozen people to the hospital.

The crane went up as crews worked to remove the scaffolding in the afternoon. The process involved lifting and removing it from the building before setting it down in the plaza below, BGE said.

READ MORE: Shootout Between Cars Speeding In Hampden Rattles Otherwise Quiet Neighborhood

Roads in the area were closed as a result of the work. The city said Fayette Street was closed from 7 a.m. to 8 p.m. Saturday.

The blast happened just before 8:30 Wednesday morning. While the building was mostly empty due to the holidays and the COVID-19 pandemic, construction crews were working on the air handling and boiler system.

RELATED COVERAGE:

Damaged scaffolding hangs from the side of the BGE building in downtown Baltimore two days after an explosion shook the building, injuring 21 people.

READ MORE: Former Baltimore Homicide Prosecutor Faces 88 Charges For Using Privileges To Stalk, Harass & Extort

First responders rescued 23 people from the building, 21 of whom were taken to hospitals. Nine people were critically injured.

As of Thursday, 12 had been released.

The blast is believed to have been caused by the construction work on the air handling and boiler system and was not gas-related, BGE said.

 

Crews will remove the crane on Sunday.

MORE NEWS: Police Identify Baltimore Officer Who Killed Barbershop Shooting Suspect

This story was updated on December 26, 2020.

CBS Baltimore Staff